The Construction Technology of Subway Large Section Subway Station Construction Channel Picking Top Into the Main Hole Construction Technology
DOI: https://doi.org/10.62517/jcte.202506112
Author(s)
Mingrui Shen1,*, Shenghui Yao1, Fei Wang2
Affiliation(s)
1School of Civil Engineering, Henan Polytechnic University, Jiaozuo, Henan, China 2China Communications Fourth Engineering Bureau Second Engineering Co., Ltd., Luoyang, Henan, China *Corresponding author
Abstract
Concealed excavation station as a commonly used way of subway station construction, mainly used in the complex surface environment does not have the conditions of open excavation in urban areas, through the auxiliary channel into the station body for construction. Due to the large cross-section of the subway station, the general auxiliary channel into the station needs to be picked up to find the top of the channel construction, the traditional top of the channel will generally be higher than the station body tunnel, the need to use concrete backfill the gap between the two, the construction cycle is long, over-excavation and backfill volume. In view of the above problems, this paper innovatively puts forward a new construction method of construction channel picking top into the main tunnel, and uses finite element software to simulate the rationality and feasibility of this method. This method adopts two-layer primary arch, i.e. gantry + station main arch arch support, which makes full use of the primary structure of the picket channel, reduces the arch change construction, reduces the amount of over-excavation and backfilling, and effectively ensures the construction period.
Keywords
Large Cross-Section; Excavated Station; Construction Access; Numerical Simulation; Arch Replacement Construction
References
[1] Luo Guangcai, Chen Zhanglin, Lu Zhiqiang. Research on excavation technology of subway station with large section and shallow buried concealed excavation [J]. Construction Technology, 2020, 49(19): 114-117, 120. [2] Zhao Ying. Research on the construction technology of the main tunnel of transverse passage conversion of super-large section concealed excavation subway station [J]. Municipal Technology, 2019, 37(2): 140-143, 198. [3] Jiang Yian, Zou Tao, Peng Xuefeng, et al. Construction technology of large cross-section and small clear distance urban tunnel opening section through scattered rock pile [J]. Construction Technology, 2021, 50(10): 55-58. [4] Li Yayong, Deng Yihu, Jin Xiaoguang, et al. Research on construction method of construction channel and station conversion section of concealed subway station [J]. Journal of Railway Science and Engineering, 2016, 13(7): 1352-1358. [5] Diao Zhigang. Discussion on construction method of cross passage and large section tunnel intersection[J]. Railway Construction, 2007, 47(10): 35-37. [6] Lv Zhiqiang. Construction technology of excavation and support for large cross-section tunnel with soft surrounding rock[J]. Construction Technology, 2020, 49(13): 51-55. [7] Yang Rui, XIE Shuai, WANG Bo, et al. Key technology of roof picking construction of inclined shaft into normal hole in adjacent fracture zone stratum[J]. Construction Technology (in English), 2024, 53(16): 50-54+91. [8] Sun Yanyang. Research on the construction technology of picking top of subway station with oversized cross-section concealed excavation station[J]. China Residential Facilities, 2023, (08): 142-144.